The land for our future home.
Day one - October 13th - We officially got started!
Excavator started building the driveway!
Day Two - The basement hole was dug!
Day Four - Forms for the basement walls were setup.
Week one - Basement walls were poured.
It took 11 cement trucks to complete the basement walls.
It only took 8 minutes to unload each truck, so every 10 minutes a new truck would arrive.
Not even two weeks in and the basement is framed.
The roof trusses were set.
Three weeks - Started framing the garage.
The septic tank was installed.
One month - The roof is shingled.
The weather has been great!
It is amazing how much has changed in one month's time.
No comments:
Post a Comment