Thursday, November 11, 2010

The land for our future home.

Day one - October 13th - We officially got started! 
Excavator started building the driveway!   

Day Two - The basement hole was dug!

Day Four - Forms for the basement walls were setup.

Week one - Basement walls were poured.  
It took 11 cement trucks to complete the basement walls.
  It only took 8 minutes to unload each truck, so every 10 minutes a new truck would arrive. 

Not even two weeks in and the basement is framed.  

The roof trusses were set.


Three weeks - Started framing the garage.


The septic tank was installed.

One month - The roof is shingled.
The weather has been great!
It is amazing how much has changed in one month's time.